Politics
Grid Collapses 105 Times In 10 Years Despite $1.4 Billion Loans
Despite the huge investment in the power sector, the national grid collapsed about 105 times under the administrations of President Bola Tinubu and his predecessor, Muhammadu Buhari, The PUNCH reports.
Findings on Sunday showed that Nigeria secured about 10 loans worth $4.36bn from the World Bank over the past decade to address key challenges in its power sector.
Although not all 10 World Bank loans have been disbursed completely, the Federal Government and other multilateral agencies have supported the country’s power sector financially.
They have provided billions of naira to revamp the industry but despite these funds, the sector is still struggling, witnessing incessant grid collapses, which has repeatedly plunge the country into widespread blackouts.
Both Buhari and Tinubu, members of the All Progressives Congress, promised to turn things around positively in the power sector.
However, it appears the challenges of the power sector overwhelmed the Buhari administration, which took over former President Goodluck Jonathan of the Peoples Democratic Congress.
Data obtained from different sources, including the Nigerian Electricity Regulatory Commission, showed that the grid collapsed approximately 93 times during the eight-year rule of Buhari, from June 2015 to May 2023.
The national power grid, according to NERC, is a vast network of electrical transmission lines that link power stations to end-use customers across the country and it is designed to function within specific stability boundaries, including voltage (330kV ± 5.0 per cent) and frequency (50Hz ± 0.5 per cent).
“Any deviation from these stability ranges can result in decreased power quality and, in severe cases, cause widespread power outages ranging from a partial collapse of a section of the grid to a full system collapse.
“When the electricity demand is higher than the supply, the grid frequency drops. Conversely, if supply surpasses demand, the frequency increases. In reaction to the grid operating at a frequency outside of the normal operation range (especially when the frequency is too low), safety settings on generation units may cause the units to shut down.
“This often exacerbates the frequency imbalance on the grid thereby causing more generation units to shut down resulting in a full or partial system collapse,” the regulator explained.
The PUNCH reports that anytime the grid collapses, the majority of electricity consumers are thrown into darkness, affecting businesses and social activities.
Industry data showed that under Buhari, the grid collapsed three times in 2015, 28 times in 2016, 24 times in 2017, 13 times in 2018, and 11 times in 2019.
The grid frequency appeared to improve from 2020 to 2023 as the grid collapsed 14 times within this period until Buhari vacated office on May 29, 2023.
It was observed that the Tinubu administration carried on with the grid collapse cases, with three of such incidents occurring between June and December 2023.
Nigerians endured more nationwide blackouts on September 14, 2023 when the grid collapsed due to a fire on a major transmission line.
On September 20, 2023, The PUNCH reported that Nigeria witnessed another round of widespread blackouts across the country the preceding day as the national power grid collapsed again, making it the third grid collapse in about five days during that period.
Since January 2024 till date, the grid has collapsed about nine times. Last week, the grid collapsed three times with its attendant blackouts, sparking reactions from Nigerians. As of now, the Tinubu administration has recorded no fewer than 12 collapses in 16 months.
On Saturday, the national grid collapsed – third in the week – as power generation went off around 8:16am. This was after the grid tripped off on Monday. It went off again on Tuesday when it was being restored.
World Bank loans
Nigeria secured about 10 loans worth $4.36bn from the World Bank over the past decade to address the power sector challenges.
The loans, which are aimed at supporting infrastructural development, distribution reforms, and renewable energy initiatives, are at different stages of progress.
While some are still disbursing, others have been signed but are yet to begin disbursement. However, one loan approved in 2014 has been terminated.
Findings by The PUNCH from data sourced from the global financial institution revealed that four loans, amounting to $2bn, have been signed but are yet to disburse any funds.
These include the Sustainable Power and Irrigation Project, valued at $500m, which was signed in September 2024, and three components under the Nigeria Distributed Access through Renewable Energy Scale-up Project, totalling $750m, approved in December 2023.
Five loans are actively disbursing funds, though large portions of their allocations remain undrawn.
These include the Power Sector Recovery Performance-Based Operation, the North Core Regional Power Interconnector, the Nigeria Electrification Project, and the NG-Electricity Transmission Project.
Together, these projects represent $2.06bn, or 47.25 per cent of the total loan portfolio.
Out of the five loans currently under disbursement, Nigeria is already making repayments on three of them.
One example is the Nigeria Electrification Project, which has disbursed $269.67m from a total allocation of $350m.
Similarly, the North Core Regional Power Interconnector has released $15.74m from a $27.4m facility. The NG-Electricity Transmission Project, with two components worth $486m, is also disbursing funds while repayments are ongoing.
These projects reflect the country’s efforts to balance loan repayments with the need for critical infrastructure investment.
One project has been terminated. The Nigeria Power Sector Guarantees Project, initially valued at $125m, was cancelled on May 1, 2014, without any funds being disbursed.
The terminated project was aimed at improving electricity supply for consumers by supporting private sector-led investments in power generation and distribution.
It was designed to back key reforms in Nigeria’s power sector through a series of partial risk guarantees.
These guarantees were intended to support three key areas: greenfield Independent Power Producers’ projects, the privatisation of Generation Companies, and the turnaround of distribution companies.
However, this project was terminated, and nothing was disbursed by the World Bank. There was no available information on the reason for the termination.
The PUNCH learnt that World Bank loans were usually tied to targets, and failure to meet such targets would either lead to a delay in disbursement or outright cancellation of the loan.
Despite the World Bank’s funding support over the years, delays in disbursement remain a significant concern, as $2.96bn of the total $4.36bn are still undisbursed.
The largest disbursement so far has been recorded under the Nigeria Electrification Project, which focuses on improving rural and off-grid energy access. So far, $269.67m has been released from the $350m earmarked for the project.
Notably, a substantial portion of the loans was secured under President Tinubu’s administration, highlighting the government’s renewed push to revitalise the country’s energy sector.
Since Tinubu assumed office in May 2023, the World Bank has approved new electricity loans over $1.901bn, representing 44 per cent of the total loan portfolio over the decade.
In December 2023, Tinubu’s government secured $750m for the Nigeria Distributed Access through Renewable Energy Scale-up Project, a move aligned with the administration’s focus on expanding renewable energy.
Also, the Sustainable Power and Irrigation Project, valued at $500m, was signed in September 2024 to enhance power generation and agricultural irrigation.
While the loans reflect a strategic commitment to addressing Nigeria’s energy deficit through renewable energy and infrastructure development, the slow pace of disbursements raises questions about project implementation and the government’s ability to unlock the full potential of these funds.
Despite the loans, the Nigerian power sector still suffers incessant blackouts, metering gaps, and low access to electricity, especially in rural areas.
Many industries, small businesses, and companies, among others, have collapsed as a result of the poor supply of electricity in Nigeria. This is despite the privatisation of the successor power generation and distribution companies in November 2013.
- Top Stories15 hours ago
Senate Suspends Rule To Pass Bill On Iragbiji Federal University
- Top Stories14 hours ago
Federal Govt ‘MDAs’ Salaries Between October-December To Be Delayed’
- Politics17 hours ago
N585m fraud: EFCC submits preliminary report on Betta Edu to President Tinubu
- News18 hours ago
Russia fines Google $20,000,000,000,000,000,000,000 000,000,000,000, more than the entire world’s GDP
- Entertainment15 hours ago
‘I Have Been Battling With Kidney Disease For 12 Years’ – Nollywood Actress Ufuoma McDermott
- Entertainment15 hours ago
TRENDING: Watch How Bobrisky Was Forcefully Taken Out Of London Plane (VIDEO)
- Tech10 hours ago
UK skilled worker visa extension 2024: Key updates on new regulations
- Top Stories16 hours ago
ZENITH BANK RECORDS REMARKABLE TRIPPLE-DIGIT TOPLINE GROWTH AS PBT HITS N1.0 TRILLION IN Q3 2024